Click below to access links

Cover Story

Off-Site Facilities Approach Help PNGTS Become a Reality.

Products

Services

News

Modular System Design Brings LNG Plant On-Line.

Background & Qualifications

Employment

©2000 Northstar Industries, Inc. Northstar Industries is a registered trademark of Northstar Industries, Inc., Reg. U.S. Pat. and Tm. Off. The American Gas Association is a registered salesmark of The American Gas Association. All other trademarks are the property of their respective owners.

Featured on the cover and as the lead story in the April 1999 Pipeline & Gas Journal and December 1999 Pipeline & Gas Industry magazines:

Off-Site Facilities Approach Helps PNGTS Become A Reality.

Since the introduction of natural gas in the northeast in the 1950's, The New England natural gas market has endured a shortfall of peak pipeline capacity due to its distance from major pipeline supply points in the Gulf of Mexico. Historically this shortfall has been supplemented with peak shaving capacity of LNG and LPG facilities. The advent of deregulation, coupled with clean air regulation, has created an unprecedented demand for baseload natural gas that can best be met with additional pipeline capacity. In response to this need, the New England energy community has tried to develop projects that would increase natural gas supply and capacity in New England from Canadian markets.

One of the proposed projects for bringing this gas to market was the Portland Natural Gas Transmission System (PNGTS). After spending more than two years obtaining federal and state regulatory approvals, the long-awaited development of this new natural gas pipeline quickly became a reality.

PNGTS is widely viewed as a win-win situation for the economy and the environment. It has become an investment in clean energy infrastructure that was sorely lacking in northern New England.

The new pipeline is used to supply a variety of customers throughout the region. It provides expanded service to gas utilities in Maine and New Hampshire and, for the first time, supplies some of the area's largest paper mills with clean-burning natural gas.

     

PNGTS will also provide fuel to some of the proposed new gas-fired power plants recently announced. In fact, these electric power projects represent more than $1 billion worth of additional economic investment in the region and, with their highly efficient technologies, will help promote competition and lower the costs of electric power.

The project involved the construction of 148 miles of 24" mainline, and 43 miles of 12" lateral pipeline in Maine. An additional 100+ miles of 30" pipe on the PNGTS/Maritimes & Northeast joint pipeline was also constructed.

Once completed the project would deliver gas from the tie-in point in East Hereford, Quebec to the existing New England gas infrastructure at Haverhill, Massachusetts. Along the pipeline's route new and existing power plants and paper mills, as well as new and existing LDC's would be given opportunities for gas supply never before available.

Project Approach:

To meet the rigorous demand schedules, the project used the following approach:

  • Define the project team
  • Establish the design baseline with preliminary engineering.
  • Procure long lead items.
  • Premanufacture all top-side facilities.
  • Install facilities in the field.
  • Provide testing, commissioning and training.
  • Provide project data book documentation.

Define The Project Team:

The PNGTS operating company was formed early in the process. This resulted in a hands-on group of experienced gas people being involved from start to finish of the project.

Because of their experience in project management of large projects, Bechtel Corporation of San Francisco, California was selected as the prime contractor.

Northstar Industries, Inc. of Methuen, Massachusetts was selected as the manufacturer of all top-side facilities for the new project in order to meet the seven-month field construction schedule.

Preliminary Engineering Process Top Side Facilities:

Prior to procurement or construction of a single facility, a preliminary engineering report was completed for each facility. During preliminary engineering, the framework for the job was established. This was accomplished by bringing together all interested parties (prime contractor, pipeline contractor, operations personnel, end users, regulatory agencies, etc.) to thoroughly define the design criteria of the top-side facilities as well as the construction interface points.

Reporting:

A report was distributed upon completion of preliminary engineering which defined the following for each facility:

  • Design Criteria
  • Site Plans
  • Geo-technical Bore-Hole Investigations
  • Piping and Instrumentation Diagrams (P&ID's)
  • Plan View and elevation view drawings
  • Cost & schedule
  • Material list
  • Job completion deliverables List

Results of Preliminary Engineering:

The preliminary engineering process resulted in identification of 23 top-side facilities for the project. Five specific premanufactured designs were defined to meet the requirements of the 23 different sites.

The top-side facilities included the following:

  • Four single building gate stations complete with measurement, preheat, regulation and satellite data acquisition/control equipment
  • Fifteen remote satellite controlled mainline valve facilities.
  • One mainline odorization facility with satellite SCADA .
  • Three launcher/ receiver facilities.
  • Host SCADA facility.

Prior to construction of the facilities, an engineering and construction plan was developed to ensure a desirable outcome in a compressed seven month construction period.

Premanufactured Meter and Regulating Facilities:

A unique design philosophy was employed in the fabrication of the four original PNGTS gate stations. A three module, single building, premanufactured design was employed to minimize cost by controlling facility size and time spent on site.

The first module in the station was considered as the hazardous area room, and contained all high pressure gas piping. Prefiltering was accomplished using Peerless horizontal particulate filters. Measurement was performed using Equimeter Auto Adjust II turbine meters, communicating directly with the Bristol RTU's. A Mercury Mini AT was mounted on the meter to provide backup measurement.

Preheating was accomplished using a shell and tube heat exchanger mounted in the gas room. Two remote Teledyne Laars water heaters equipped with Taco pumps, quietly and efficiently circulated hot water/glycol around a fire wall to the shell and tube heat exchanger.

A three way valve with pneumatic temperature controller damped the glycol/water and controlled outlet gas temperature.

Pressure regulation was accomplished using parallel sets of Grove 900 TE's (working monitor and downstream worker configuration) along with a Becker Super Monitor (for fire and single incident overpressure protection) and token relief valve.

All I/O including pressure, temperature, boiler control, meter outputs, flow control, gas/fire/smoke detection, was all wired back to the DAC Module (Data Acquisition and Control) which housed the RTU's, UPS and Satellite Communication Systems, all within a temperature controlled environment.

The entire facilities were premanufactured entirely off-site by Northstar in their Methuen, MA manufacturing facility. This lowered the overall cost of the job by minimizing time on site by construction personnel.

Premanufactured Main Line Valve Control Sites:

Fifteen main line valves (MLV's) were installed on the PNGTS System, to allow for local/remote operation of the valves. Each MLV control building consisted of an 8' x 8' x 10' monolithic concrete building. Each building was shipped with two precast concrete grade beams. This eliminated the need for costly concrete and iron work at each site, and enabled field personnel to set foundations and buildings in under 24-hours at each site.

Each of the stations were outfitted with the following equipment prior to being shipped to the site:

  • Bristol 3305 RTU
  • Lamarche UPS System w/Johnson TCV battery bank
  • AC breaker panel
  • DC breaker panel
  • Remote CP monitoring equipment
  • HVAC system
  • Satellite communications equipment
  • Voice and backup data telephone equipment
   

Once installed in the field the MLV's were used to open and close valves, sense valve position, sense upstream and downstream pipeline pressure, and monitor remotely the pipeline cathodic protection readings. The building and RTU were designed to accommodate remote rectifier control for future expansion.

Premanufactured Mainline Odorization Facility:

Odorization of the PNGTS pipeline is accomplished shortly after the pipeline enters the United States from Quebec, Canada. To minimize costs, the facility was located at a main line valve facility.

In addition to all the equipment installed at the other MLV sites, the mainline odorization facility was equipped with a larger building. The building contained a 3,000-gallon ASME-250 odorant storage vessel, and redundant NJEX-8200 Odorization System used to accomplish proportional-to-flow odorant injection.

The doors and penetrations of the building were raised 12" and the floor was epoxy sealed to provide 110% secondary containment of the odorant storage vessel as required by NFPA 30.

All odorant lines were welded to eliminate break points and potential odors. All equipment and piping was installed by Northstar prior to shipment to the field.

Premanufactured Launcher/Receiver Facilities:

Four launcher/receiver facilities were installed on the pipeline to allow for future internal inspection of the pipeline using intelligent pig technology. One was fabricated and installed by Trans Quebec and Maritime at the completion of their pipeline in Canada. Three other facilities were installed as follows:

  • Completion of a 24" line in Portland, ME
  • Kickoff of a 12" lateral in Albany , ME
  • Completion of a 12" lateral in Jay, ME

To minimize field costs, the barrels were manufactured, tested, and coated in Northstar's manufacturing facility and then shipped to the field for tie-in. To further minimize costs, the launcher/receiver sites were placed at either main line valve or gate station facilities, thereby eliminating additional driveway, fencing, and other associated site work.

Host SCADA Facility:

Since PNGTS was an entirely new pipeline, no existing SCADA center or control room existed. To minimize personnel costs, it was determined that an existing gas control center would be hired to maintain the PNGTS SCADA System on a 24 hour basis. Providence Gas Company was chosen as the host control center for the project. A modular host server system was developed knowing that one day it might be removed from its temporary home to a permanent facility manned by PNGTS personnel.

During preliminary engineering the Bristol RTU's were selected to deliver field I/O through Nova Net, Inc.'s Satellite Network. From Nova Net's hub in Colorado, data would be routed via a T-1 line to a server. Bristol Open BSI would control the data in the server, with Intellutions providing the HMI Graphical Interface. PNGTS remote network capability would be added to allow for viewing the SCADA remotely at various PNGTS operations facilities in Maine and New Hampshire.

The basic functional SCADA system was completed by Northstar during the aggressive seven month construction phase. Deliverables for networking, and data base storage continue to be added at this time.

Procurement and Manufacturing:

Once the preliminary engineering was completed and approved by all involved parties, the procurement process was completed. All materials were shipped to Northstar's manufacturing facility in Methuen, MA. Once there all materials were installed in precast, six sided, monolithic, concrete buildings.

All facilities were welded, hydro-tested, painted, wired, tubed, labeled, tagged, and loop-checked in a controlled environment in the plant. This process ensured not only quality control, but eliminated the costs associated with travel, storage, and lodging over the traditional, on-site construction process. Once completed, the facilities (some weighing more than 95,000 lbs) were loaded by crane on low-bed trailers and transported from the manufacturing facility directly to the field location. Once set in the field, a facility could be made functional and ready for operation in less than one day.

Site Construction:

Since the majority of the work on the facilities was completed off-site in Northstar's manufacturing site, a minimal amount of work was required on-site. The work on-site consisted of the following:

  • Installation of foundation (precast on smaller buildings);
  • Placement of precast, premanufactured buildings;
  • Installation of ground grid, zinc grid, electric service, phone service, and signal wire;
  • Alignment and testing of satellite dish equipment;
  • Erection of fence and gates;
  • Finishing of grade and stone installation;
  • Installation of driveway and protective bollards;
  • Check out of field I/O.

By staging materials and developing specialized crews, the average site was completed by Northstar in only eleven working days on site.

Commissioning:

Commissioning was completed in five days in late February, 1999. The first customer using flowing gas was recorded March 9, 1999. In less than 10 months from the beginning of top-side facilities procurement, all facilities were successfully activated.

Project Data Book:

In order to ensure proper project documentation a Northstar Project Data Book was developed for each station and the host SCADA system. This comprehensive book was born upon acceptance of the preliminary engineering. It served as a living, changing document, outlining all details of design, manufacturing, testing, and site construction of all top-side facilities. A typical project data book included the following:

  • Design criteria by discipline;
  • Calculations;
  • As-built drawings;
  • Material test reports (MTR's);
  • Weld procedure and qualification information;
  • NDT results;
  • Hydrostatic and concrete test results;
  • Manuals and cut sheets for all major equipment.

The data books serve as a record of what was manufactured to assist operation's personnel during maintenance and operation of the facilities.

Summary:

The PNGTS project strengthened New England's natural gas portfolio and allowed the addition of new baseload and peak customers in Northern New England that were previously not served by pipeline gas.

The formation of an experienced PNGTS operating staff in the early stages of the project added to the overall success of the effort.

The project approach of preliminary engineering sign-off prior to detailed engineering, helped ensure a desirable project outcome. The preliminary engineering served as a template for the Project Data Books, which captured all necessary design, manufacturing, component, Q/A test, and site construction information for each facility.

Northstar's patented approach of manufacturing single building top-side facilities entirely off-site helped make a seven-month field construction period possible, and simplified pipeline operations and maintenance.

To learn more, or to receive a free Modular Systems Brochure, call Toll Free 877-975-5500.
Or send an e-mail to us at:
info@northstarind.com


126 Merrimack Street, Methuen, MA 01844

Tel: (978)975-5500 Fax: (978)975-9975

| Home | About Us | Background |Employment | Services | What's New | Site Map |

©1999 Northstar Industries, Inc. All rights reserved. Product specifications are subject to change without notice. Reg. U.S. Pat. and Tm. Off.